KB Sentral Project Faces Three-Week Soil Treatment Setback

The KB Sentral integrated bus terminal project in Kota Bharu has slipped 21 days behind schedule in its soil treatment phase, with work now at 40.07% completion instead of the planned 47.26%. Authorities blame persistent heavy rains and prefabricated drainage delays.